West Deptford Energy Solutions

Owner: West Deptford Energy Solutions

Location: West Deptford, NJ

Overview

Schwertner completed all of the Concrete Work for the Combined Cycle Plant. Project included all sitework and electrical. Foundations totaled 1350 tons of reinforcing and 16,000 CY of concrete. Highlighted by the Steam Turbine Pedastal (pictured), which was a 1,250 CY (12’ Thick) pedestal formed on columns that were 40’ tall.